Scope of work
1. Remove/ Installation provide by Azbil (Thailand) Co.,Ltd.
Pick-up the valve site permitted area to Azbil workshop by Azbil.
2. Pretest / Inspection /Disassemble /Cleaning/Lapping/Part replacement /Assembly
/ Function test/Pressure test /Calibrate/Painting /QC provide by Azbil (Thailand) Co.,Ltd.
3. Crane and driver and 4P rigger provide by Sumitomo Rubber.
4. Scraffolding and Insulation provide by Sumitomo Rubber.
5. Local spare part supply by Sumitomo Rubber.
6. Price are excluded re-machine /modified (if any ) price will charge later.
7. Overhaul valves report after work completed will be report by Azbil (Thailand) Co.,Ltd.
8. Working schedule : 30 Dec 2016 to 3 Jan 2017.
9. Hiab transportation (if any ) provide by Azbil (Thailand) Co.,Ltd.
10. Blind flange thin (Thk 5 mm.) for close pipe flange provide by Azbil (Thailand) Co.Ltd.