If I can ask you to prioritise queries from the following the stations teams first;
• 1B2 & 2B4
• 1B1 & 1A2
• 1E2
As these are the stations which have base slab or cradle slab design packages already issues or very close to being issued.
The focus for you at the minute should be to get the basic principles resolved so we can issue our a guidance note to each of the station teams.