The range (a, b) encloses all possible estimates of the duration of an activity. The estimate
m lies somewhere in the range (a, b). Based on the estimates, the average duration
time, D, and variance, v, are approximated as:
CPM calculations given in Sections 6.5.2 and 6.5.3 may be applied directly, with D
replacing the single estimate D.