I made the status of your order K1502 in attachment.
I would like to make some explanation:
The washing mitt and duster:
We sometimes have stock textile fabric. For example, if you order 1500pcs of mitts, I need to weave the fabric for 5000pcs.
If we have stock fabric, we can finish the goods in 10 days after your confirmation.
Now we don't have enough stock fabric for these 2 items, we have woven the fabric and sent to dying factory.
Because of environmental polution, dying factory is far away from our area, dying will take around 10 days.
PVA chamois: The lead time for PVA chamois is always around 25 days. We can't keep tubes in stock as they will get dirty.
The tubes are always newly produced in other factory and will be delivered to our factory for packing.
Now, based on the status of these 3 items, we are trying to get the goods ready before Oct.31, and inform you the fastest shipping date.