Dear khun Alessandro,
I want to information the process of pile cutting at site by the picture only.
Process today;
Buffer tank; the process of pile cut 0 % ( tomorrow plan to do excavation and pile cut off to be complete )
Storage tank; the process of pile cut 100 % ( tomorrow plan to do drilling and addition DB and extend the pile cap )
T040 tank; the process of pile cut 95 % ( tomorrow plan to do pile cut and fill soil high maybe 30 cm around tank )
T041 tank; the process of pile cut 15 % ( tomorrow plan to do soil cut down maybe 30 cm deep around tank )
Post Digester the process of pile cut 65 % ( tomorrow plan to do pile cut and fill soil high maybe 45 cm around tank )
Best Regards,
Adul T.