Thank you for your extra work on this matter. Manuel’s concern was that the printed name on the cable did not match the name on the test report of the cable and therefore the test report could not be trusted. Although we understand that this is the cable that was tested in China, all safety precautions should be taken before and during commissioning of the installed cable. Thus SAT testing must be completed as planned and when energizing the cable people should be inside the station building for their protection.