To be inform
Infrastructure work
-PMC coordinate with ofbore well Underground water will be installed
at location near to pond for filling water.
- JWS to push infrastructure to be complete the end of July.
-JWS to start infrastructure work at beside road Devasom Hotel
complete the end of month.
Fitness, Pool Bar ,Kids Club
-JWS will be the roof install next month to be complete and handover
to MEP and ND.
-Water Fall 2 & 3 to be finish by next month