Further our below email and the meeting on 12th Jun 2014, for the item no. 13 (GEG synchronzing),
we hereby provide you with our engineering review and test results.
The 1st test was succeed, however, the 2nd test was failed by damage (transient surge) of UPS.
So, it was modified not to be used this function, as it is very dangerous situation.
However, if UAC request to do test one more time by using load bank for normal condition, it would
be tested at UAC cost. (However, in case of test failure by defect, this cost will be borne by SCT)