We would like to know further explanation why the 2nd shipment is delay & only today we’ve been informed on this matter?
This shipment should reach HMMMY on 25th July as we need to do unpacking on 26th July.
Information also has been explained by Mr. Nizam in his email to Busarin San on 27-June.
After taking the timeline for clearance process, it is impossible to meet the schedule accordingly.
As you know this shipment inclusive of Y230 model which we have set the goshi unpacking check and production with the involvement of HML & HMMI members.
We need to explain to our top management and arrange for back-up plan.