Dear All
As we move forward, NH has identified which joinery pieces will be assigned for the upcoming series:
YP and CV - Please review the intended sequence for you - which will match the client approved Const Docs delivery schedule:
11 Event Hall 2014-03-30
13 Gym&Fitness 2014-04-11
12 Arrival 2014-04-30
16 Kids&Teens 2014-05-31
15 Retail 2014-05-31
16 Library 2014-05-31
17 Restrooms 2014-05-31
N:128.26 Ritz Carlton Langkawi5 Source In16 BF_BKKFrom NHNH Sketch2014-03-20YP - CV_Public Area Joinery
Please think about your design timeframe and be prepared to discuss with RF later this afternoon.
Please ensure that your proposed/draft schedule considers
• Your design time
• review w RF
• CAD time
• Your CAD review/redline
• CAD redline completion
Ideally, approved sketches are delivered to CAD progressively.
Be considerate and please aim to allow minimum 4 days CAD time before the upload deadline.
Thanks
DW