Project Crashing and Time-Cost Trade-Off
General Relationship of Time and Cost
• Project crashing costs and indirect costs have an inverse relationship.
• Crashing costs are highest when the project is shortened.
• Indirect costs increase as the project duration increases.
• Optimal project time is at minimum point on the total cost curve.