While FERC’s jurisdiction is limited to large, interstate transmission lines utilized by wholesale energy generators, states tend to follow FERC’s lead. The agency’s 2005 standards-which established the first set of interconnection procedures for wholesale electricity generation projects under 20 MW in size-were adopted by many state and remain in place today