The loading bay sections will be fitted together at ground level to foam the Skelton off the frame.
This will then be hoisted up to L25 by derrick crane to waiting workers move to position and bolted down to concrete floor slab back props 2" jacked to undersize of L26 floor slab and the wire cable tension ropes will be fitted to front of loading bay and secured back to L26 face of slab