Thank you so much for your info and doesn't worry for all prepare.( everything can change every time. :)
Well noted and for all document I will keep it first so and tomorrow I will work at the Bangkok office normally.
Finally I will wait inform from you for next process.
Now schedule
23 Dec - set up transfer on a pole. (Thaikajima will set up security for safe transformer after set up finished.
22 - 24 Dec - CAT arrange cable line.
28 Dec - Request Engineer PEA for check a power box and all set up.