Master Schedule.
Once the design scope of work is finalized, the PM amends the Master Schedule to include a detailed design schedule. The Master Schedule should have design, review, agency approvals, and permitting milestones to include:
- Schematic design, review periods, and cost estimate preparation.
-Value engineering and constructability reviews.
-Design development, review period, cost estimate preparation.
-Agency approvals, time and funding authorization milestones.
-Construction document completion, whit approval time at appropriate percentage of completion, accompanied by review periods and cost estimate preparation.