Once in place it was energis as well.
The concrete
foundations for the new steel strain monopoles were then
cast in two stages and allowed to cure for the recommend
period of seven days to achieve the 20 MPa strength
required. The copper-clad steel counter-poise earths were
laid before the tower template was concreted in place to
prevent theft in the future as it would not be visible after
the base foundation was covered again with backfill top
soil and compacted.