Material Storage - is dunnage and weather protection being used.
• Materials - are the correct approved materials being used per Bayer Regional Standards.
• Tracing - is tracing installed and heat transfer media in place (if required).
• Release - has the item to be insulated been tested (leak, pressure, etc.)
• Painting - has painting, if required, been completed.
• Safety - are workers wearing required and recommended protective equipment and working in accordance with plant safety policies.
• Securement and Fit-up - are the insulation materials tightly fitting and secured properly.
• Joint Sealing and Vapor Barrier Coating(s) (Cold Service) - are joints being sealed thoroughly and
vapor barrier coating installed in accordance with Bayer Standards.
• Jacket Fit-up - is metal fit-up close, tight, neat, and oriented to shed water.
• Metal Edges/Bands - are overlaps rotated properly, edges hemmed 1/2", and bands and tabs installed to prevent sharp edges.
• Caulking - has required caulking been installed in a neat workmanship manner.
• Accessory Materials - have pipe insulation shields been installed and banded in place.
• Clean-up - has daily and work completion clean-up been performed.