Dear Sale Dept.
This below detail from K.Worapan (ISUZU-PPG) , She request to conclusion as below ;
1. This change will effect to Tooling : Block Screen and Block Copy
(For Price , Please consideration from size , process and Tooling Change effect also)
2. The Schedule of Tooling and Development New Sample will complete within 3.5 week after
receive Final File data , Drawwing and PH-Film.
Anyway for more information with need to receive for refer cost or anything , Please confirm by Feasibility format
to K.Mongkol / K.Saranya / K.Sommai again (This Just draft Detail).
** Please kindly Contact Customer **
Best regards,