7 DEBUGGING
7.1 Mechanical drive partial debugging
The EJH-14 -L/H conveyer belt transports type:
1) Connect and turn on the power source.
2) Press lightly "DEBUG" the button on the control panel, set equipment to the debugging condition.
3) Press lightly the control button, and the electrical machinery run, please
observe for 5 minutes to check whether the electrical machinery revolve steadily, or the conveyer belt deflect or not. If it deflects, please defer to: Adjustment, until the movement of conveyer belt is steady.
4) Pat the conveyer belt, observe whether the constriction of the conveyer belt is appropriate, whether the conveyer belt will rub the detector head or not. If it is too loose or too tight, please adjust as below: