Today, we have an appointment with Aware. To install Generator and ATS switch in Data Center project. In this morning at 8:15 generator truck had arrived at STEC and need to install generator but don’t have staff from Aware arrived at this time to control. Make unable to perform or decided to proceed. I must be coordinated through by phone. Which may cause an error. So I need Aware should determine when it is time to have been installed in the core interference please assigned who is responsible came to the STEC with the contractors to perform properly.
And the evening I have to check the tidiness of installing a generator and have found gasoline that there is drop down surface from a generator, which is very dangerous if it sparks. Please check the abnormality as soon as possible.