Summarytasks are automaticallyscheduled and not manuallyscheduled by default .
The duration of an automaticallyscheduled summarytask is calculated by Project as the span of time from the earliest start date to the latest finish date of its subtasks.
If you directly edit the duration of an automaticallyscheduled summarytask, or its start or finish date, it will be
switched to a manually scheduled task .