I set the priority as below, because I though RPCL 2 sets has a few pieces and TGO engineer can finish quick.
As to Senoko, I want to confirm the number of accessary parts for CB earlier (in order to prepare more), so I gave priority to CB 2 sets, and TP later.
If you want to change the priority, let me know.
(We can change the priority, but can not finish earlier...because we have only 1 engineer assigned to review CB&TP report.)