with reference is made to the above contract and article E-28 : Extension of Time, If, by reason of any of the Any other unforeseen circumstance beyond the Contractor's control. because supplier's delivery by use ocean vessel HANJIN NETHERLANDS which caused bankruptcy, affect vessel can not docking port at Singapore
We would like to inform you that the can not delivery the equipment for schedule A2 B2 and C2: 115 kV Disconnecting Switch and Con June 25, 2016 and the equipment would be arrived Bangkok port around July 29, 2016. Therefore, we would like to request you to issue a letter of approval for shipment.