Please help me organize with safety FORD team for the work fix the fire pipe leak at EDC-1 as we walkthrough last Monday ago,
That I plan start work on tomorrow morning by details
- 1. Rental Articulating boom lift will arrive EDC-1 about 8.00 am.
- 2. TD team working 3 persons 1. I’m Warakul 2.K.Khomsan 3. K.Somsak use boom lift get up for make point leak in the pipe about 8.30 am
- 3. Drain water in pipe line on 9.00 – 10.00 am. *** Maybe have noise alarm signal (Kong) from header fire pipe
- 4. Weld the pipe block leak point and painting 11.00 am
- 5. Test system by filling water in the pipe line 12.00 am – 13.00 pm
- 6. If no have leak mark ,the job finish , When still leak I must re-start the work at step 3.