This schedule gives us almost no breathing room for delays and completes about 1 month delayed from our submitted schedule. This is a big risk. Why are the gaps between the installation dates so far apart, did EdL give a reason, specifically from 07 Feb – 27 Feb where no work is being completed.
A silver lining as you mentioned to me is that if they are shutting down the feeders then we can install our cable. Can you confirm that we will be able to install our power cable in Thakhek during these times as well? If so, we need to have Enova provide us with a installation plan aligned with this new shutdown schedule ASAP.