ATTN : K'Usanee/JTEKT
For your consideration, attached is TPK confirm plan to JTEKT and request part from ABT on June"16 in attached files.
As you may have noticed, for part 2DUF054N-2K-TC.
TPK has had back order from May : 14,400 Pcs. (TPK loss capacity in the beginning of month : ABT delay delivery raw materials)
and refer from JTEKT delivery plan that request part on 2 June :14400 Pcs. TPK can produce the part just only 10800 Pcs, so TPK will get more back order 3600 Pcs.
(TPK still can't make stock on this week)
To recovery all back order, we are planning to produce the part and recover back order on 6 June (10800 Pcs.) and 24 June (7200 Pcs.)
For part 3DACF027F-1.
TPK has had back order on 30 May : 9600 Pcs.(ABT delay delivery raw materials : received 3200 pcs. on 27 May and 6400 pcs. on 29 May)
To recover back order, we have to receive part from ABT constantly as appear in attached fire.
Please let me know if I can do more to support this.
Best regards,