1. Review Drawing.
2. Issued master schedule(APQP).
3. Open Meeting.
4. Follow trial event each until MP1.
- Tooling schedule and follow status tooling transfer from japan.
- Machine schedule and prepare check spec M/C.
- Preparation raw material for trial.
- Issued document trial request sheet.
- Trial result Problem history review and analyze cause.
- Trial result out put / Part weight / Runner weight / Cycle time record.
5. Issued document Inspection standard and control point check.
6. Make BOM (Bill of material) / Master Part List.
7. FMEA
8. MSA (Bias,Linearity,Stability,GR&R)
9. Flow chart , Control Plan
10.CF jig prepare and Tooling prepare
11.Design packing std for new product / Label / Drob test
12.Make process condition chart
13.PPAP
14.Training to operator of each process before Mass production.
15.Process monitoring and improvement.