In February 2009, a mobile crane and a small piling rig appeared on site. In early March 2009, the crane began putting steel beams into the ground, as part of preparations for the core of the building. Full construction began on 16 March 2009. Demolition work on New London Bridge House started in May 2009, as part of the concurrent London Bridge Place project. The first steelwork went into the Shard's piles on 28 April.