The below is my plan to get the set back down to 250kips
1. We have 66stds in the derrick of 5 ½” dp that was just picked up for this hole, we’ll keep this.
2. We’ll lay down 82 stds of 5 ½” dp and it’s to be backloaded to be inspected.(we’ll need 30jts of 5 ½” dp sent to the rig)
3. We’ll lay down 6 stds of 5 ½” hwtdp we have 3 jts on the deck also all will be sent in for inspection (we’ll need to get the 19 jts sent out to us that’s in storage)
4. We’ll lay down the and send in the 6 jts of 8 ¼” DC to be inspected, we have 6 jts on the deck that we can use.
With the 66stds of 5 ½”dp, 60stds of 4”dp and 7stds of 4”hwtdp we’ll have 255kips in the set back (128tons)
Raksit,
We need to get the 30ea jts of 5 ½”dp and 19jts of 5 ½”hwtdp on the next available boat that way it’s here on the rig for the move.