Dear Rolan,
I would like to update status for MSW power plant project as item below,
· MOU sign-off plan to completed within end of this month (November)
· MSW component study and test after MOU sign-off and take time around 3 weeks
· Feasibility study will start after MOU sign-off also and take time around 6 weeks that mean we will got a report around mid of January 2016. (Include concept design, financial model, process and etc.,)
So about your idea, when we need to continue for work out of financing proposal again? Please help advise.
Regards,