FRP Vent Line Replacement Job
1. We are taking a plant shutdown from 6th Sep to 19th Sep 2016.
2. We intend to take up this job during that time window.
3. We hope to finalize and release PO only on Monday.
4. Please inform the following :
(i) Time Required to Complete the Job
(ii) Start Date of the Job
5. We also need to point out that we shall provide ONLY the following items :
FRP Pipe
FRP Elbow
FRP T-Way
FRP Nozzle
Nut, Bolt, Gasket, Washer as required
ALL other material and accessories as required shall be required to be arranged by Vendor ONLY
Scaffolding shall need to be arranged by Vendor only.
We have only limited scaffolding which may or may not be sufficient/safe for this job involving height.
6. Since this job involves height, please ensure the following :
(i) Submission of Job Safety Analysis (JSA) for the job duly discussed and approved by our Safety Officer
(ii) Certificate to use the Scaffolding
(iii) Deployment of people with experience to work at Height.