As it was delivered by K Tum, could you brief the situation of output decrease
in a formal report? This is a critical issue at this moment since there is
possibility of re-do performance test. We believe that the last performance
test failed to meet the guarantees under the contract. Any loss of output
can raise issues of liquidated damage and legal dispute. Please pay keen
attention to this issue. Thank you.