I understand the constraints (equipment availability and rainy season) but I can also see the increasing pressure from Corporate to make sure we progress fast on this matter.
Let's make sure that as soon as we have a window of opportunity (rain slowing down) we mobilize the necessary equipment to progress on the works to be done - even if this means to contract another supplier to perform these civil works.
Regarding the update of the safety factor, are we on track to get the safety factors updated by end September?
This is important to respect this deadline in terms of credibility (as we have already missed the June deadline).