In the event that, during the Net Capacity Test carried out as contemplated by paragraph 3 of Part B of Schedule 10, the specification of the Primary Fuel does not conform to the specifications provided for in the Onshore Construction Contract, the Contractor shall have no liability to the Operator under clause 3.2 of Part B of Schedule 10 in respect of the guarantee of the Target Bottoming Cycle Net Heat Rate of such CC Block for that relevant Net Capacity Test.