Due to some price from the suppliers not quote to us and some MTO not finished, I would like to postpone our quotation for Lighting, Lightening, Receptacle Bulk Material from today to tomorrow. But our submission schedule for each building as shown bellowed;
1 Substation, Inlet Filter Separator Shelter, Gas Compressor, DIESEL TANK SHELTER, Guardhouse within tomorrow
2 Remaining Shelters within Friday
3 Control Building within next week
4 Warehouse to be advised later
Please be informed.