2.2. Pilot setup of a SBE recovery plant
A pilot SBE recovery facility was established at Pasir Gudang. The pilot plant was equipped with an open door and a closed door composting systems having composting piles of about 8′ (height) × 8′ (width) × 16′ (length) at the initial 30 days and enlarged at 18′ × 24′ × 60′, respectively after 60 days on maturity.