Punishment:
8.1: In developing this construction project, if party (A) does not perform to pay the fee of heavy machines and laborers to Party(B) on time as required, Party (A) shall be punished 1% (one percentages) of each payment amount during 5 days to party(B).
8.2: In the case of Party(B) does not complete the performance of the construction project following to the contract in the period and phases of completing the project of each phase then party(A) shall make a punishment of that phase for 1%(one percentage) from party(B) during 5 days too.