The assembly period will implicitly be extended in the case of force majeure by the period for which force majeure
continues, plus appropriate start-up time, and the Customer shall not be entitled to any damages or other claims, except
in the event of unlawful intent or gross negligence by rommelag ag. Unforeseen circumstances beyond rommelag ag's
control that complicate or thwart assembly work beyond what may be expected of rommelag ag is equivalent to force
majeure. Examples of force majeure are mobilization, war, civil war, theorist activities, riot, sabotage, industrial disputes,
lock outs, disturbances in the firm, including temporary shortages of suitable labor, accidents, sickness, delayed or faulty
supplies of the necessary materials, acts or omissions of the authorities or government bodies, unforeseeable obstacles
to transport, fire, explosion and natural events, rommelag ag will be relieved of any obligation to provide assemblers
should such circumstances extend beyond 4 months.