Asbestos
An updated asbestos survey of any building or section of a building that is scheduled for renovation or demolition shall be conducted to identify both friable and non-friable asbestos containing materials. A draft copy of the survey must be reviewed by the University Asbestos Coordinator for completeness prior to accepting the final product. A copy of the updated survey must be kept on site until the renovation or demolition activities are completed.
The survey shall be conducted prior to the start of renovation or demolition under the supervision of a Florida-licensed asbestos consultant. Individuals performing asbestos surveys must be certified as EPA asbestos inspectors through a Florida-approved training provider.