Dear Piya/ Senior team
Next Friday we have to propose to business for how can we manage to receive product from Wangnoi 4500 pallets to storage in our warehouse from January 2015 then we have to prepare on
1. How many aisle we need to reserve for product from Wangnoi.
2. We have to start bring pallet that have less case to pick face for reduce pallet in reserve location(should start now) but it's always have new coming pallet.
3. We have to start block location that we reserve for Wangnoi (should be start block on 15th Dec) and start block from aisle 33 backward.
More information that we need
1. When is start date and end
2. Volume incoming per day
3. Type of truck, side load or back load
4. Do product is coming and out in the same time? if yes, what estimate through put per day?
5. System and document to support this project.
6. Can DHL bring their own staff&MHE to support this project?
7. Who responsible for stock take
8. No need to transfer account for pallet Loscam?