The Contractor shall, as specified in the Contract or as instructed by the Engineer,
allow appropriate opportunities for carrying out work to:
(a) the Employer’s Personnel,
(b) any other contractors employed by the Employer, and
(c) the personnel of any legally constituted public authorities,
who may be employed in the execution on or near the Site of any work not included
in the Contract.
Any such instruction shall constitute a Variation if and to the extent that it causes the
Contractor to suffer delays and/or to incur Unforeseeable Cost. Services for these
personnel and other contractors may include the use of Contractor’s Equipment,
Temporary Works or access arrangements which are the responsibility of the
Contractor.
If, under the Contract, the Employer is required to give to the Contractor possession
of any foundation, structure, plant or means of access in accordance with
Contractor’s Documents, the Contractor shall submit such documents to the Engineer
in the time and manner stated in the Specification.