Dear All,
Refer to system 19T - TRUCK LOADING on P&ID Final walk down on 8-10 October 2015, Please find attached Final walk down punch list issue for your information and action.
Dear K.Sitta, and concern,
Could you please review and confirm for additional work items (Item1,2 of 19T) before issue to sub-contractors for start work.
Dear SAS TECH, UCS, MSL,
Punch list as attached for your action punch clear ASAP.
Note : I had edit punch items separate for system
03N - TRUCK LOADING (Non P&ID)
19T - TRUCK LOADING (on P&ID)
Punch for 19T that new punch as show in yellow and indicate to punch Date.
Dear All,Refer to system 19T - TRUCK LOADING on P&ID Final walk down on 8-10 October 2015, Please find attached Final walk down punch list issue for your information and action.Dear K.Sitta, and concern,Could you please review and confirm for additional work items (Item1,2 of 19T) before issue to sub-contractors for start work.Dear SAS TECH, UCS, MSL,Punch list as attached for your action punch clear ASAP.Note : I had edit punch items separate for system 03N - TRUCK LOADING (Non P&ID)19T - TRUCK LOADING (on P&ID)Punch for 19T that new punch as show in yellow and indicate to punch Date.