P-17 Proposal conducting the test of existing equiptment.
Here we have it, the proposal conducting the testing of existing equipment prepared by LTE for your review. Below is also their clarification to explain how the works will be conducted into 2 stages. Apparently the project will need to allow in the budget the restoration cost of the equipment (if required) to make it suitable and safe for testing. This cost is yet unknown until the phase one work as outlined below is conducted.
We would like to clarify the scope as follows;
Phase 1: condition assessment is to determine that main equipment in the suitable condition to test or not. This phase is try to avoid risk of damaging equipment by proceed testing without suitable equipment condition.
Because equipment has never been used for long time and also has never been periodic maintenance as per suppliers recommend. Therefore, equipment surly need to assessment, restoration, changing some parts and other necessary actions shall be performed for equipment in suitable condition before test.
Phase 1 report shall give you suggestion term of restoration cost, restoration method and warrantee. If restoration cost is more than buying new one, equipment replacement choice might be suitable for your project.
Phase 2 on site equipment test
After your determine condition assessment in Phase 1, some equipment does not need restoration. There can be performed testing on site.
However, some equipment need to be restored before test. Owner shall also be accepted restoration cost (recommended in phase 1) to make equipment in suitable condition before test.
Moreover, some equipment shall be done on supplier factory but some equipment shall be done on site. But after restoration work finish supplier will issue warrantee to those equipment.
EquipmentTesting shall be performed after restoration stage.
Phase 2 report shall give you each equipment testing results, guarantee, warrantee.
P-17 Proposal conducting the test of existing equiptment.
Here we have it, the proposal conducting the testing of existing equipment prepared by LTE for your review. Below is also their clarification to explain how the works will be conducted into 2 stages. Apparently the project will need to allow in the budget the restoration cost of the equipment (if required) to make it suitable and safe for testing. This cost is yet unknown until the phase one work as outlined below is conducted.
We would like to clarify the scope as follows;
Phase 1: condition assessment is to determine that main equipment in the suitable condition to test or not. This phase is try to avoid risk of damaging equipment by proceed testing without suitable equipment condition.
Because equipment has never been used for long time and also has never been periodic maintenance as per suppliers recommend. Therefore, equipment surly need to assessment, restoration, changing some parts and other necessary actions shall be performed for equipment in suitable condition before test.
Phase 1 report shall give you suggestion term of restoration cost, restoration method and warrantee. If restoration cost is more than buying new one, equipment replacement choice might be suitable for your project.
Phase 2 on site equipment test
After your determine condition assessment in Phase 1, some equipment does not need restoration. There can be performed testing on site.
However, some equipment need to be restored before test. Owner shall also be accepted restoration cost (recommended in phase 1) to make equipment in suitable condition before test.
Moreover, some equipment shall be done on supplier factory but some equipment shall be done on site. But after restoration work finish supplier will issue warrantee to those equipment.
EquipmentTesting shall be performed after restoration stage.
Phase 2 report shall give you each equipment testing results, guarantee, warrantee.