In the meeting at Site on last Thursday, 15th Sep 2016, I got information about time schedule of electrical/ control panel and relative equipment arrival (for Turbine building) as below;
1. Low Voltage electrical panels will be delivered all not later than 15 Oct 2016
2. Battery, Battery charger will be arrived on 24 Oct 2016
3. Diesel Generator will be arrived on 24 Oct 2016
4. Transformer will be arrived on 30 Oct 2016
5. Switch gear will be arrived by the end of November (approximate 30 Nov 2016)
So From these schedule, We would like you to aware of some works which Neo civil has to do and complete it after Last equipment arrive and install such as a brick wall work, Plastering and Painting, Ceiling and rubber floor tile which will take approximately not later than one month from the date stated (if weather is not getting so bad).
Then I would like to reserve of time for this extension period just to avoid any conflict with purchase agreement.
For your perusal and consider approve krub.