1) Concrete work for well cellar will be started the day after tomorrow
2) Concrete work for drilling pad will be started next week
3) Concrete shale shaker will process parallel with cutting pit – plan start after complete concrete drilling pad
4) Conductor pipe will be installed by 1st week of Apr’14
5) Drilling of water well is ongoing