Dear Kh.Berry,
According to the weekly meeting about progress of construction last week ,Prairie propose some issue to as below
1.Prepare documentation on request filed factory expansion before on 20 Nov 14
2.Start adjusting retaining wall area “Scale for Truck” to the slope in to pond,and planted grass
3.Conclusion : the wall behind the control room.There will be built the bench along the wall.
4.Prairie will send the details around the building drain dryer for later.
5.Schedule for test run
- 24 Dec 14 Test Run Machinery : Action by Prairie
- 29 Dec 14 Test Run PLC : Action by CR Team
- 30 Dec 14 Test Run All System : Action by Prairie,CR Team,Cornucopia
- 5 Jan 14 Test Run By Product : Action by Prairie,CR Team,Cornucopia