As K Za mentioned, during discussion with department Industrial , it will take some time to get the license
During this period, we are not allow to let both “cullet and rubbish” out of the company
So, we have to manage 15 ton/day of “good cullet PWS, PSL, PBL” , 2-3 ton/day of “mix cullet” and 6-8 ton/day “LWS with PVB cullet”
There is 15+3+8 = 26 ton/days
Cult will be full at scrap yard in a few days
Pakorn,
Have you finish supplier selection, this is TOP urgent
Please at least ask them to take “LWS with PVB cullet”
The “good cullet PWS, PSL, PBL” and ““mix cullet” are sellable , we can discuss separately