Dear P'Boonsong,
Regarding supplier did not accept for the sorting cost because there concern with the packaging design that cannot protect the humidity and temperature since we started business with them. BTW, I tried to put them to add the VCI paper or VCI bag and now their management already approved following e-mail below.
So, as we have one lot (4,419 pieces) was blocked area (5800) now. can we call out sort to support sorting first and pay money by Continental cost? Kindly please confirm.
And FYI, this case is not urgently, because we have part for support production in warehouse (5100) about 89,540 pieces as capture below.