1. Background and Objective
the pumping system is having all six pump working. All pumps are of CVP 1450.
the discharge line is connected to siphon making and breaking arrangement.
The system is connected through common header to collect the total dis charge.
However, during power failure, due to breaking of the siphon, each pipeline will be acting as individual system. Thus we have considered one system for the analysis.
All the sections of the ducts are converted to equivalent pipe diameters. Objective of this analysis is to study the system for surge conditions and suggest suitable protection devices to control the surge in the system.