First of all, thanks for your help in this project with PepsiCo.
The procedure of our normal partnership with tank manufacturer is the following:
1) We send you our draft drawings of tanks and platforms
2) You prepare your own fabrication drawings
3) You send us the drawings and we’re checking the overall design and the positions of mounting part. If all is correct you’ll receive our “ok”.
4) The parts which we indicate on our drawings with * would be supplied by Miteco. We will send you those parts within the next 4 weeks
Generally notes:
- Static design would be under Dhawath responsibility
- All platform walkways ladders need to meet the ISO standards 14122 and latest amendments
Please find attached the first part of tanks
Should you need further information’s or should you have questions